SAFE Workflow Guide

How to run a Scaled Agile Framework (SAFe) workflow using this template. Covers what maps well, what needs workarounds, and what is not supported.

SAFE Levels Supported

Level Support
Team Full — sprints, stories, tasks, kanban
Program (ART) Partial — PIs via Milestones, Features, cross-team tracking
Large Solution Minimal — Capabilities not natively supported
Portfolio Minimal — Epics by label convention only, no cross-project rollup

This template is optimised for Team and Program level SAFE.


Program Increment (PI) Setup

A PI is typically 10 weeks (5 × 2-week sprints). Use a GitHub Milestone to represent each PI.

# Create a PI milestone
gh api repos/OWNER/REPO/milestones \
  -X POST \
  -f title="PI-1" \
  -f description="Program Increment 1 — 2026-Q1" \
  -f due_on="2026-03-27T00:00:00Z"

# Assign a Feature to PI-1
gh issue edit ISSUE_NUM --milestone "PI-1"

# Also set the PI custom field on the project item
gh project item-edit --id ITEM_ID --project-id PROJECT_ID \
  --field-id PI_FIELD_ID --text "PI-1"

Sprint / Iteration Setup

Iterations are managed on the project board. Create a new iteration at the start of each sprint:

  1. Open your project board in the GitHub UI
  2. Go to Settings → Iteration field
  3. Add a new iteration with name (Sprint 1), start date, and duration (14 days)

Or via GraphQL:

gh api graphql -f query='
  mutation($project: ID!, $field: ID!) {
    addProjectV2IterationFieldIteration(input: {
      projectId: $project
      fieldId: $field
      startDate: "2026-01-06"
      duration: 14
    }) {
      iteration { id title }
    }
  }' \
  -f project="PROJECT_ID" \
  -f field="ITERATION_FIELD_ID"

PI Planning Process

  1. Create the PI Milestone with due date at end of PI
  2. List candidate Features — create issues with Type: Feature, assign to the PI Milestone and set PI field
  3. Decompose Features into Stories — create sub-issues under each Feature
  4. Estimate Stories — set Size and Estimate fields
  5. Assign to Iterations — commit Stories to specific sprints via the Iteration field
  6. Set PI Objectives — create a pinned Feature-type issue per team titled PI-N Objectives listing committed objectives and stretch objectives

Work Item Hierarchy

GitHub supports 2 levels of parent-child. Use the following mapping:

Milestone: PI-1
│
└── Feature (issue, Type: Feature, milestone: PI-1)
    │   Title: "User can authenticate with SSO"
    │   Parent issue: (none)
    │
    ├── Story (sub-issue, Type: Story)
    │       Title: "User sees SSO login button on login page"
    │
    ├── Story (sub-issue, Type: Story)
    │       Title: "User is redirected to IdP on SSO click"
    │
    └── Enabler (sub-issue, Type: Enabler)
            Title: "Configure SAML 2.0 provider integration"

Epics that span multiple PIs:

Label: Epic
Milestone: (no single PI — spans PI-1, PI-2)
Features reference the Epic in their body with "Part of #EPIC_NUM"

Sprint Cadence

Event When GitHub action
Sprint Planning Day 1 Assign Stories to Iteration, set Start date
Daily Standup Daily Check board status — filter by Iteration
Sprint Review Day 14 Review Done items, demo to stakeholders
Sprint Retrospective Day 14 Create an issue Type: Enabler with retro action items
PI Planning Last sprint of PI Create next PI Milestone, populate Features

Known Limitations

These are structural gaps in GitHub Projects v2 for SAFE. Each has a recommended workaround.

1. Hierarchy max 2 levels

Gap: SAFE needs Epic → Feature → Story → Task (4 levels). GitHub supports 1 level of parent-child (Feature → Story).

Workaround: Model only Feature → Story in the hierarchy. Epics are tracked by label and Milestone grouping. Tasks are inline checklist items in Story issue bodies.

2. No Program Board / dependency visualisation

Gap: SAFE PI Planning produces a Program Board showing Feature dependencies across teams and their iteration commitments. GitHub has no dependency graph view.

Workaround: - Use a blocked-by label convention: add to an issue's body Blocked by #N - Link issues explicitly using GitHub's "linked issues" feature - For cross-team dependencies, create a shared tracking issue per dependency

3. No native WSJF calculation

Gap: Weighted Shortest Job First requires 4 inputs (Business Value, Time Criticality, Risk Reduction, Job Size) and a calculated output. GitHub Projects v2 has no calculated fields.

Workaround: Add numeric custom fields for each WSJF component, then run a scheduled GitHub Action that reads them, computes the score, and writes the result back to the Priority field. This Action is not yet included in the template — contributions welcome.

4. No PI Objectives construct

Gap: SAFE uses formal PI Objectives with Business Value scores agreed with business owners.

Workaround: Create a pinned issue per team per PI titled PI-N Team Objectives. Use a table in the body with columns: Objective, BV Score (planned), BV Score (actual), Status.

5. No capacity planning

Gap: SAFE sprint planning includes per-person capacity (accounting for leave, ceremonies, etc.) compared against story point commitments.

Workaround: Add capacity as a comment on the Iteration planning issue. The Estimate field sum per sprint can be read from the API for comparison.

6. Cross-project portfolio rollup

Gap: If you have multiple repos/teams with separate project boards, there is no native way to aggregate status at portfolio level.

Workaround: Create a dedicated portfolio project board and manually add cross-repo issues to it. Or script a nightly Action that queries each team board and posts a summary issue to the portfolio board.


Metrics

Velocity

# Story points completed in an iteration
gh project item-list PROJECT_NUM --owner OWNER --format json | \
  python3 -c "
import sys, json
items = json.load(sys.stdin)['items']
velocity = sum(
    int(i.get('estimate', 0) or 0)
    for i in items
    if i.get('status') == 'Done' and i.get('iteration') == 'Sprint N'
)
print('Velocity:', velocity)
"

PI Predictability

Predictability = (Actual BV delivered / Planned BV committed) × 100%

Track planned vs actual BV on the PI Objectives issue.

Flow metrics

The pi-report.yml Action generates a weekly snapshot of per-Status counts (Todo / Ready / In Progress / In Review / Done / Awaiting Decision). For flow efficiency and cycle time, export the board data and analyse in a spreadsheet or BI tool using the Created and Closed date fields.